Arunachal Police Housing Welfare Corporation Ltd. takes the challenge to construct buildings in the remote and difficult terrain with an inadequate road communication, network connectivity & power supply to support its future development

Physical achievements of some Project


FS-Tawang.jpg (5529 bytes)

30-B-Hawai.jpg (63652 bytes)

OP Tali.jpg (6714 bytes)

Construction of Fire Service Building at Tawang

District -Tawang : High altitude varies from 3500 feet to 22500 feet approximately. Building materials not available locally & transported from Assam about 12 hrs. journey by road.

Construction of 30 Men Barrack at Hawai

District - Anjaw : Located at an altitude of 1296 m on the banks of River Lohit, Hawai is the administrative headquarters of Anjaw District. Building materials not available locally & transported from Assam.

Construction of Out Post Building at Tali

District - Kra Daadi:- Located at an altitude of about 1700 mtr. It is a remote Area, head load is required to carry raw materials about 20 kms on hilly terrain from motorable road end to reach the site by one day foot march. Cost of one bag cement is about Rs. 2500/-. Building materials not available locally & transported from Assam.

Construction of Police Station Building at Anini

District - Dibang Valley : The district hqrs Anini is located at 1968 meters above sea level. It is a remote area, raw materials are transported from nearest district hqrs. Roing and Assam. The road communication is disrupted during rainy season for 5-6 months and occurs frequent road blockage. Due to this, there is huge cost index.

Fire Service Building at Yingkiong

District - Upper Siang: The district hqrs. Yingkiong located at about 2000 mtrs above sea level. It is a remote area, The road communication is disrupted during rainy season and occurs frequent road blockage. Due to this, there is huge cost index.